Authority approves pipeline change orders and time-limited contract extensions after BLM and SCE delays
Summary
The board approved Provost & Pritchard change orders totaling $130,031 for imported water pipeline design and environmental services and agreed to time-limited contract extensions (item 15 continued to January; item 16 modified to 03/31/2026) to keep the project moving while staff provides additional operational cost estimates.
The Groundwater Authority approved change orders to the imported water pipeline contracts and took time-limited actions on related contract extensions after staff and consultants described schedule delays tied to Bureau of Land Management permitting timing and later-than-anticipated design work from Southern California Edison.
Provost & Pritchard (represented at the meeting by Jeff Helsley) described two change orders: a $109,965 increase for additional design project-management/coordination and a $20,066 increase for…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat