Delray Beach CRA cancels RFQ for West Atlantic redevelopment, will restart with RFP as remediation work continues
Summary
The Delray Beach CRA voted to cancel a request for qualifications for the Northwest 800 block of West Atlantic Avenue and reject all submissions, saying a new request for proposals will give the board visuals and clearer proposals; staff warned remediation of an underground plume tied to Atlantic Avenue remains unresolved.
Get email alerts on the West Atlantic Redevelopment topic
No spam. Unsubscribe anytime.
The Delray Beach Community Redevelopment Agency voted to cancel a request for qualifications for redevelopment of the Northwest 800 block of West Atlantic Avenue and to reject all submitted qualifications, a move staff said will let the agency restart the procurement with full proposals and design visuals.
"We are today seeking to cancel this request for qualifications and reject all submitted proposals," Ray Jaddis, the CRA executive director, told the board as he framed the decision as a procedural reset. The board voted unanimously to accept the recommendation.
Why it matters: staff and commissioners said the earlier RFQ produced team qualifications but not the visual proposals the board and community wanted to see. Board members also said the agency now controls more land in the area — roughly two acres on the south side of Atlantic Avenue — which changes the development options and may make a grocery store or other larger user feasible if parcels are rendered contiguous.
Environmental constraint: staff briefed the board on a long-running groundwater contamination investigation tied to a former gas station and an underground plume beneath West Atlantic Avenue. Staff said consulting work and quarterly testing show the plume has remained largely contained for nearly 20 years but is located under FDOT-owned Atlantic Avenue. "Remediation in that location is difficult, because it would require closing down, you know, significant portions of West Atlantic Avenue," the staff presentation said, and the CRA will ask consultants for a detailed future-options report describing what can be built under various remediation outcomes.
Board reaction: Commissioners acknowledged the burden on proposers. "I do feel a little bit bad about this because I know the other applicants spent probably considerable resources to bring us those presentations," Commissioner Long said, urging caution about the optics of restarting a process. Other members said restarting with an RFP will provide clearer, visual proposals earlier in the process.
Next steps: staff said the CRA will proceed to draft an RFP and may pursue abandonment of a small platted alley to create a contiguous parcel, which could improve prospects for a grocery store or larger retail user. The CRA also intends to obtain a more explicit consultant analysis of remediation options before issuing the RFP.
The agency's vote to cancel the RFQ was procedural; no developer was selected and no contract was awarded. The CRA set a special meeting for Dec. 4 to continue West Atlantic plan discussions and to consider a work assignment tied to the procurement schedule.