Committee hears why Campbell County bus facility is overbudget; agency estimates $6–$8M shortfall
Summary
Officials told the committee Campbell County’s bus facility is over budget due to a site change, poor soils, and unusually large bus counts (about 150 buses); the agency estimated a current shortfall of $6–$8 million and said the stadium portion of the high school will be bid first with ground work in early spring.
Agency staff updated the committee on construction work in Campbell County, saying the new high school is in early design and the transportation facility (bus barn) has exceeded initial budget estimates because of a site change, poor soils and extensive parking requirements.
Miss Carlson said high school design is between roughly 10 and 35 percent and that the district planned to advance a stadium package first. She said a smaller package to prepare temporary…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat