Historic commission adds Woolworth intensive survey to work plan, directs staff to draft budget
Summary
The Springfield Historic Commission agreed to add an intensive‑level survey (ILS) of the Woolworth Building on Main Street to its 2026 work plan and instructed staff to prepare a detailed budget and scope; commissioners urged keeping the city request under $10,000 while seeking partner contributions.
Get email alerts on the Historic Preservation Woolworth Ils topic
No spam. Unsubscribe anytime.
The Springfield Historic Commission voted to add an intensive‑level survey of the Woolworth Building at 612 Main Street to its 2026 work plan and directed staff to return with a detailed budget and implementation plan.
Karen Johnson, a consultant with the Springfield Renaissance Development Corporation (SRDC), told the commission the two‑story, midcentury Woolworth Building is “historic quality is very much intact” and that an ILS would document architectural features, measured drawings, photographs and research that could inform future reuse tied to the adjacent Wildish Theatre.
The ILS request emerged after SRDC’s October application to the Oregon Heritage Commission was referred to the local commission. Johnson said the full scope could require imaging such as ground‑penetrating radar or wall scanning to determine whether a common wall could be altered safely, and estimated the work at roughly $10,000–$15,000 depending on whether external imaging and paid contractor time were required. She said a University of Oregon preservation team could supply student labor and faculty oversight in some parts of the project.
Commissioners and staff discussed grant requirements and procurement thresholds: the Certified Local Government (CLG) framework and State Historic Preservation Office (SHPO) guidance require professional qualifications for contractors under an ILS, and requests under $10,000 avoid the city’s higher procurement thresholds. Commissioners repeatedly urged limiting the formal city request to under $10,000 and using SRDC or private partners to cover or help fund specialized imaging if needed.
One commissioner disclosed multiple conflicts of interest — membership on the historic commission and SRDC and a client relationship with the building owner — and said they would manage those roles transparently. During debate, members also explored using a student national‑register project or breaking tasks into separate pieces (imaging vs. documentation), but SRDC and others cautioned that splitting the ILS could harm continuity for a student team and reduce overall quality.
A motion was made and seconded directing staff (Tom and Elise) to prepare a budget and work plan that includes the Woolworth ILS, heritage award medallions, a window workshop, a railroad plaque and consultant fees. The commission voted to adopt the motion; the chair recorded one abstention (Jenna) and stated the majority were in the affirmative.
The commission did not appropriate final funds at the meeting. Staff were directed to return in January with a recommended budget and specific dollar amounts and to clarify which tasks the city would fund directly and which partners would support, including any imaging costs that may fall outside standard ILS line items.