Valley Center receives construction update on new water treatment plant; slab targeted for Dec. 12
Summary
Project superintendent Reid Harmon said the backwash basin is complete, process building grade beams are poured and staff aims to pour the building slab by Dec. 12; the process building could be 'dried in' by March with green sand vessels delivered around June.
Reid Harmon, project superintendent, updated the council on the water treatment plant construction on Nov. 18, saying crews started work around July 1 and that completing the backwash basin allowed the team to begin work on the process building and underground piping.
Harmon said process-building grade beams are poured and about one foot of aggregate is in place. If crews…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat