Committee reviews MSBA comments, schedules filings and debates EV chargers and school security
Summary
Project team told the committee MSBA required a DESE resubmittal over changing‑table changes in special‑education rooms; members discussed permitting timelines, Fano Drive site acceptance, EV charging station counts and reliability, and questioned the scale of security card‑readers in the new elementary school.
The Stoughton School Building Committee spent much of its Dec. 10 meeting reviewing design, permitting and operational issues for the proposed elementary school.
Project consultant Eric (project team) told the committee the Massachusetts School Building Authority (MSBA) issued comments on the design‑development package and required a DESE resubmittal after plans changed to add or relocate changing tables in special‑education rooms, which in turn required an updated narrative and plans. Eric said the consultant team (DRA) had worked with the district and planned to return the revised package to MSBA by the end of the week.
The project schedule: 60% construction documents were sent to estimators; estimates are due Jan. 5, with a reconciliation Jan. 9 and final reconciled estimates by Jan. 16. The team said it…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat