County roads and bridges update: demolition, culvert replacements and winter preparations

St. Francois County Commission · November 25, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Roads and Bridge staff reported clearing trees, demolishing the old Augsburg Bridge ahead of new beams expected mid‑to‑late February, replacing numerous culverts and prepping equipment and routes for the winter season.

County roads and bridge officials told the commission they have begun demolition work on the old Augsburg Bridge in preparation for placement of new beams expected in mid‑to‑late February and have been replacing numerous culverts ahead of planned overlays.

Roads staff reported clearing trees on the county line, replacing roughly 15–20 culvert pipes along Cedar Run and completing milling and patching work on other routes. Officials said the new culvert pipe is a heavy‑wall PVC smooth-bore product intended to flow more water and resist flame damage from yard fires compared with older black pipe. "It's a smooth bore which will flow more water," Speaker 1 said.

Staff said they are training newer employees on plow routes and turnaround spots and performing snow‑and‑ice equipment maintenance to prepare for winter operations. Work on several overlay projects was delayed by weather but crews expect to complete contractor-led paving when conditions allow.

What’s next: bridge demolition will continue and crews will await delivery/placement of new beams; winter readiness and route familiarization for new employees will continue.