Rhinebeck board continues review of Rembrandt/White House hotel amid traffic, water and wastewater concerns
Summary
The Rhinebeck Planning Board continued the public hearing on the Rembrandt/White House LLC hotel proposal to Jan. 6, 2026 after residents and board members pressed the applicant on traffic at Route 9G, well testing and the size/visibility of a proposed wastewater treatment facility.
Get email alerts on the Land Use Development topic
No spam. Unsubscribe anytime.
The Rhinebeck Planning Board on Dec. 1 continued its review of a proposed hotel complex brought by Rembrandt Villas/White House LLC, citing outstanding traffic, water-supply and wastewater-treatment questions that both neighbors and the board said need more technical detail.
Sean Kemp, speaking for Rembrandt Villas, said the project team will provide additional documentation requested by board staff and consultants and that they are supplying the long-form environmental review materials the board asked for. "We plan on, obviously, supplying that information," Kemp said, asking the board to allow more time for CEQR/SEQR analysis.
The board and multiple residents focused on three issues that remain unresolved: how traffic from the hotel will affect the Middle Road/Route 9G intersection; whether well testing and pump capacity are sufficient for a hotel; and the size, siting and appearance of a planned wastewater-treatment unit. Resident Eleanor Leiter said she had contacted the State about the intersection and asked the town to pursue a traffic study: "I called them. I wrote to them twice," she said, urging town action.
Board members and residents noted the applicant’s traffic materials include a crash analysis and a conceptual left-turn lane that NYSDOT has reviewed, but said the intersection itself still raises safety concerns. Several members urged that an independent review of the applicant’s traffic analysis be done; the board authorized staff to seek a cost estimate for an independent engineer to review the applicant’s materials and report back.
Water-supply questions dominated several public comments. Speakers cited the applicant’s testing of two neighbor wells; the applicant and staff said those tests follow state formulas for average and maximum daily demand. Board members pressed for clarity about daily and peak pump capacity, long-term drawdown effects on neighboring wells, and whether the proposed pump and storage arrangement would meet peak-hour demand for a 60-room hotel. One member summarized the technical concern: if a well can produce a large volume across a day, can it also meet high hourly demand during morning peak usage?
Neighbors also asked for more detail and visuals of a proposed wastewater-treatment container. Board members said they need a rendering showing the worst-case visible footprint with proposed screening from Route 9G and key neighbor vantage points. "Present to us the worst-case scenario, and let us see what the impact will be," a board member said.
Planning staff outlined next steps: the board will collect written questions from members and residents, give them to the applicant and the town’s consultants, and consider inviting the applicant’s consulting engineer and the town’s consultant (CPL) and an independent traffic reviewer to a future meeting. The public hearing was continued to Jan. 6, 2026.
The continuation preserves a procedural path for the board’s long-form environmental review; it does not represent approval of any permit or change to the project. The applicant was asked to provide specific, labeled materials: certified well-test documentation and methodology, maximum hourly and daily water-demand calculations, wastewater-treatment sizing and elevations, lighting plans, and renderings showing the treatment facility and proposed screening from Route 9G and nearby residences.
Next steps: the board asked for written comments and specific questions from neighbors and will coordinate consultant reviews before resuming the hearing on Jan. 6.