Riviera Beach council invites chosen developer to negotiate municipal hall complex after competing presentations
Summary
After presentations from Forest Development and Sonnenblick Development, the council voted unanimously to proceed into negotiations with the evaluation committee’s recommended team and asked staff to form a negotiation committee and return with negotiating parameters.
Get email alerts on the Municipal Hall Itn topic
No spam. Unsubscribe anytime.
The Riviera Beach City Council on Nov. 17 heard two competing proposals for a long‑planned municipal hall and mixed‑use complex and voted unanimously to move into negotiations with the developer recommended by the city’s evaluation committee.
Procurement Director Latanya Ammons summarized the ITN (Invitation to Negotiate 1106‑24‑3), saying the solicitation sought public‑private partnerships to deliver a new city hall, library and related mixed‑use development on city‑owned parcels and nearby sites. Two teams — Forest Development and Sonnenblick Development (with Kaufman Lynn and MCO among partners) — presented designs, financing plans and community benefit packages.
Forest Development described a multi‑phase plan that it said could total at least $635 million and be completed across phases in about five to seven years, with City Hall and initial civic facilities targeted in the first phase. The team pledged community engagement, local hiring targets and workforce housing for educators and first responders. Forest said portions of privately owned parcels in the study area would be purchased as part of the negotiated plan.
Sonnenblick framed its proposal around government‑tenanted buildings and pledged forms of contractual protection: the team told the council it would include a 100% performance bond guaranteeing delivery date and price and described lease terms with prepayment and buyout options (the presenters said the city could prepay bonds after year 10 and that a $1 buy‑back after 30 years is included in the lease structure).
Councilmembers questioned both teams about total costs, phasing, local participation and how parks and bond proceeds would be handled. Several asked for specific, documented commitments on local contracting and a schedule of milestones.
After public comment and attorney guidance on procedure, the council made a motion to invite the recommended respondent to negotiate (the motion cited the evaluation committee’s recommendation) and voted unanimously to approve it. City staff will bring a resolution to establish a formal negotiation committee and outline negotiating priorities for the council’s review.
What’s next: the negotiation committee will work with the selected respondent (and, if necessary, with the alternative respondent) to develop a draft agreement and return the resulting terms to the council for approval before any contract is executed.