Planning staff presented the 2026 department narrative and eight capital requests including utility undergrounding on University Avenue, EV infrastructure, LED streetlight replacements, and a tentative $300,000 B-cycle bike-share capital proposal; the commission recommended the narrative to council but voted to defer project PL2602 (community climate outreach) to 2027 because of scope and staffing concerns.
Get email alerts on the Capital Budget topic
No spam. Unsubscribe anytime.
Abby of Middleton's Planning & Community Development Department presented the department's 2026 narrative and capital budget priorities at the Aug. 12 Plan Commission meeting.
Staff said the department changed its mission statement to align with the city's strategic and comprehensive plans, and listed several priorities including a community campus plan, an affordable housing tax-increment financing (TID) extension approach, and continued work on the active transportation plan. Staff reported administering about $5 million in grant funding and finalizing reporting on another $3 million.
The department proposed eight capital projects for 2026. Staff discussed an initiative to underground overhead utility lines along University Avenue; the corridor plan excerpt referenced an approximate figure of $1,000,000 per mile, but staff said firm cost estimates are not yet available and cautioned the project depends on cooperation among utilities and private communication providers. Other proposals included EV infrastructure for city fleet vehicles, LED streetlight replacement funded in part by grants, picnic tables and a shade structure at Stonehorse Green (some to be considered by the CDA), bus shelter artwork and a downtown mural, and trailhead improvements at the Pheasant Branch Conservancy.
Staff also described a tentative B-cycle bike-share capital offer of roughly $300,000 with no annual operating cost for the city; staff submitted an MPO TAP grant application seeking $240,000 and budgeted a $60,000 local match.
Commissioners raised concerns about staff capacity to conduct a community-wide climate outreach process and the likely cost of meaningful outreach. After discussion, commissioners moved to recommend the planning narrative and budget package to the city council but to defer project PL2602 (the community climate outreach/roadmap) to 2027. The motion passed by voice vote.
What happens next: staff will develop firm cost estimates (particularly for the University Avenue undergrounding project) and forward the narrative and capital recommendations to the city council for consideration.