Steve Haley, vice chair of the Dickson County School Board, presented a high-level facilities plan to the county commission that uses occupancy, location and condition criteria and a 'green dot' student-density map; the board aims for final county action by February–March and says projects will use competitive bidding and a mix of reserve and board funds.
Get email alerts on the Education topic
No spam. Unsubscribe anytime.
Steve Haley, vice chair of the Dickson County School Board, told the county commission on Dec. (work session) the board is advancing a long-range facilities plan built around three tests — occupancy, location and condition — and that the board will aim to bring a proposal before the commission in late winter.
Haley said the board previously passed a resolution authorizing $15,000,000 for four major projects and related smaller work. "We passed a resolution for 15,000,000 for 4 major projects with some minor projects to fill in the gaps," he said, noting that some projects already are in construction or final stages, including a career-technical building at Creekwood.
The board presented several maps and charts, described in a commission packet, designed to show student density (the so-called "green dot" maps), building capacity and grade-by-grade enrollment. Haley described occupancy thresholds the board uses: when a school's reported occupancy reaches roughly 70 percent the system should plan for options; at about 80 percent a building is effectively full by operational standards.
Haley emphasized planning by feeder patterns — "If you have high school capacity, then you can build middle and elementary into them" — and said the board is focusing future expansion likely on elementary capacity in the county's south and west clusters. He also said the board will prefer competitive bidding for large projects and noted the board previously selected Lockwood Martin as architect/consultant and used RFQs for roofs and other work.
On condition, Haley said some high schools have received major mechanical and roofing work funded from reserve money and that middle schools and some elementary buildings will need remodeling or selective replacement. He said the board expects to recommend a mix of remodeling and larger projects and asked the commission for feedback as the board refines cost and scope.
The board and county agreed to a compressed timeline: Haley said the board hopes to have near-final plans for county consideration by January–February, with a target to finalize county-level approvals in March if both bodies adhere to the proposed schedule. "So March, I think, would be very realistic," Haley said.
The presentation closed with commissioners and board members agreeing to continue work-session discussions and to share additional detail at upcoming meetings. The board invited commissioners to attend its work sessions and to ask for further information on specific projects.