Huron approves $283K equipment purchase and moves forward on water-main projects

Huron City Commission · December 9, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Huron City Commission approved buying a new asphalt distributor and cleared change orders and payments for multiple water-main and street projects, with staff saying the projects remain within budget and nearly complete.

The Huron City Commission on Dec. 8 approved a $283,000 quote for a 2026 Leeboy Maximizer asphalt distributor and authorized several change orders and a progress payment for ongoing water-main and street-reconstruction projects.

City engineer Brett Runge told the commission the RDO Equipment Company quote for the distributor was $283,198 (Runge also referenced a more precise figure, $283,001.98) and that $285,000 had been budgeted for the purchase. Runge said the city aimed to finalize the purchase before an anticipated price increase of roughly 12–15% in the new year. The commission approved the acquisition by roll-call vote.

Runge also presented final change order number 3 for the 4th Street Reconstruction (Midland Contracting), noting a contract decrease of $24,563 and a final payment request of $3,188.86. He said the contractor committed to performing any reseating work under warranty next spring and that the project remains under budget despite a $20,000 change order added to reshape a site feature. The commission voted to approve closing out the project and the payment.

On the city’s water-main replacement work, Runge explained a $16,670 change order to Manning Excavating Inc. arising from the need for a deeper bore under Highway 14 to avoid boulders, resetting storm-sewer components, and unexpected sections of AC pipe. The commission approved the change order and authorized the mayor to sign.

The commission also approved pay request number 8 to Manning Construction for $419,362 as a progress payment on a separate water-main contract; Runge said the project is about 96% complete with approximately $147,000 in work remaining to finish next spring. He characterized the payment as a standard progress draw rather than a final closeout.

The commission approved all motions by roll-call votes.