Peninsula Trail bids come in far above estimate; CPC agrees to placeholder warrant articles and asks for alternatives

December 19, 2025 | Town of Southborough, Worcester County, Massachusetts


This article was created by AI summarizing key points discussed. AI makes mistakes, so for full details and context, please refer to the video of the full meeting. Please report any errors so we can fix them. Report an error »

Peninsula Trail bids come in far above estimate; CPC agrees to placeholder warrant articles and asks for alternatives
Kat, representing the town Trails project, told the Community Preservation Committee that the Phase 2 bid process returned two bids substantially higher than the CPC’s budget. She said vendors reported a roughly 25% price increase since 2023 and that one bid came in about double the earlier estimate (figures discussed in the meeting compared an estimated $211,000 baseline and ~ $427,000 bids). Kat explained the original choice of a fiberglass modular bridge was to avoid large cranes and to secure a 75‑year lifespan, but the higher bids prompted the Trails team to propose alternatives.

What was proposed: Kat outlined three options: (1) pivot to a timber bridge (she estimated timber could be 30–60% less expensive, with a shorter expected lifespan and different engineering requirements), (2) prioritize building the bridge first and defer or phase the boardwalk to avoid a ‘boardwalk to nowhere’ outcome, and (3) prepare a Town Meeting warrant article to transfer unused contingency from Phase 1 into Phase 2 or to ask voters for additional funds in a later warrant.

Committee concerns and guidance: CPC members asked about bid‑splitting risk and legal exposure; Freddie advised seeking legal opinion but said the bridge and the boardwalk can be presented as separate projects if necessary. Members cautioned against releasing all contingency funds at once; several said the committee should retain a safety net for cost overruns. The committee asked Kat to return in January with: (a) a simple comparison table (phase 1 vs. phase 2; original scope vs. potential scope changes; money spent; money remaining), (b) schematic layouts showing both the combined and bridge‑only options and what a bridge‑only alignment would mean for trail continuity, (c) refined cost estimates for timber vs. fiberglass options, and (d) a recommended contingency amount to retain.

Decision point: Rather than a final vote, the CPC agreed to prepare placeholder warrant articles (one to move available Phase 1 contingency toward Phase 2 and a second placeholder in case additional Phase‑2 funding is needed) and to revisit the issue in January when more detailed cost breakdowns and alternative schematics are available.

Ending: Kat will seek a cost breakdown from bidders, prepare alternative renderings and a concise one‑page comparison for CPC review, and return in January; the CPC signaled preliminary support for placeholders but withheld final funding decisions pending the updated materials.

Don't Miss a Word: See the Full Meeting!

Go beyond summaries. Unlock every video, transcript, and key insight with a Founder Membership.

Get instant access to full meeting videos
Search and clip any phrase from complete transcripts
Receive AI-powered summaries & custom alerts
Enjoy lifetime, unrestricted access to government data
Access Full Meeting

30-day money-back guarantee

Sponsors

Proudly supported by sponsors who keep Massachusetts articles free in 2025

Scribe from Workplace AI
Scribe from Workplace AI