Board hears construction progress at all four schools; gym and board offices on track for mid-January
Summary
Construction chair reported progress across Metuchen’s four-school construction program: high school gym and board offices expected Jan. 16, Moss completion around Jan. 20, Edgar near punch-list completion, Campbell finishing doors/hardware; energy audit and solar options remain under review.
The Metuchen Board of Education’s construction committee reported Dec. 16 that major projects at all four district schools are advancing and approaching scheduled finish dates.
Construction chair Brian Glassberg told the board the high school’s base paving, sidewalks and grading are complete and that interior work on the gym/field house and board offices is largely finished; he said the board…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat