District 58 construction update: referendum work largely committed; Herrick expected to need extra contingency

Downers Grove Grade School District 58 Board of Education · December 17, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Construction managers reported 87% overall completion and said 98% of referendum costs are committed; they asked the board to expect a December request to reallocate contingency funds to cover roughly $250,000 for Herrick.

Construction manager Jordan Schulz (Huffman Kiel) presented the board with a fall update on referendum projects on Nov. 10, saying the district is 87% complete on referendum-related construction and that 98% of projected hard costs have been committed through bid packages and purchase orders.

Schulz reviewed the phases: middle-school summer work is wrapping up with O'Neil and Herrick nearing substantial completion; elementary phase 3 bid group results were presented and the administration recommended awards on the consent agenda. He said commissioning, punch-list items and seasonal testing of mechanical systems remain.

On contingency and finances, Schulz said the owner contingency currently shows about $3.4 million available after prior pre-allocations and projected savings; he told the board that Herrick will likely require roughly $250,000 of additional contingency and that staff will return in December with a proposed reallocation to cover that overage. He also said the district is tracking estimated savings from earlier phases (Schulz cited approximately $600,000 of phase-2 savings) and some phase-3 bid savings shown in the slide materials.

Board members asked for the rationale behind alternates that were accepted or rejected for phase 3 and where work differed from phases 1 and 2. District staff and the facilities team explained that alternates were evaluated for equity across elementary schools, equipment lifecycle and whether items were critical repairs versus nice-to-have upgrades.

What the board approved: The board later approved the construction consent agenda, including phase 3 elementary bid group 2, as part of the consent items presented that evening.

Provenance: topicintro SEG 1152; topfinish SEG 1679.