Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Anderson council sets April 2026 election and approves multiple infrastructure contracts
Summary
On its year-end agenda, Anderson City Council set the municipal election for April 7, 2026 (Ordinance 25-18) and unanimously approved a three-year hydrant/valve maintenance contract (QCC Services LLC), a sewer-line repair contract (Davis Plumbing & Sewage LLC) and a water-line extension on Michelin Boulevard (Davis Plumbing). The actions were funded from the city—s utility and budgeted funds.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Anderson City Council finalized several actions at its year-end meeting, adopting Ordinance 25-18 to schedule the next general municipal election for Tuesday, April 7, 2026, and approving three separate public-works contracts for water and sewer infrastructure.
Ordinance 25-18: The ordinance sets the municipal election for April 7, 2026; staff noted the last day to register to vote for the April election is Saturday, March 7. The council approved the ordinance on its second and final reading by unanimous voice vote.
Hydrant and valve maintenance contract: Staff said Department of Environmental Services rules require exercising and flow-testing valves and hydrants every three years and that recent growth has made in-house completion difficult. Utilities staff recommended a three-year contract with QCC Services LLC of Pamlico, S.C., to exercise approximately 1,033 valves and 389 hydrants (one-third of the system) over the contract period. The low bidder was QCC at $55,605 per year ($166,815 total) and staff recommended a 10% contingency ($16,681.50) for a total authorization of $183,496.50 funded from the city—s water funds; the council approved the award unanimously.
Sewer-line repair on North McDuffie/East Dorr Street: Staff described a partially collapsed lateral that was approximately 20 feet deep and recommended abandoning the problematic segment and installing a new 8-inch pipe along East Gore Street to consolidate service for four customers. Bids were received and staff recommended awarding the project to Davis Plumbing & Sewage LLC of Iva, S.C., on a low bid of $187,000 plus a 10% contingency ($18,700) for a total authorization of $205,700 from the utility sewer budget; council approved the contract.
Water-line installation on Michelin Boulevard: Staff presented a proposal to install roughly 1,550 feet of 8-inch water main to support existing and anticipated development on Michelin Boulevard. The low responsive bid by Davis Plumbing & Sewage LLC was $157,547.25; staff recommended funding the project from utility water capacity funds and adding a 10% contingency ($15,754.73) for an authorization of approximately $173,301.98. Council approved the contract unanimously.
Council members asked about recurring maintenance costs and whether new infrastructure projects would be rolled into existing paving plans to economize on mobilization; staff said the city had reserved funds for Main Street paving after utilities work and would evaluate opportunities when projects are mobilized.
Votes at a glance: - Ordinance 25-18 (sets general election 04/07/2026) — Approved on second reading (unanimous voice vote) (SEG 675-693). - Valve and hydrant maintenance contract (QCC Services LLC) — Award approved; $166,815 base + 10% contingency = $183,496.50; funded from water funds (SEG 955-984; 1023-1035). - Sewer-line repair (Davis Plumbing & Sewage LLC) — Award approved; $187,000 + 10% contingency = $205,700; funded from utility sewer budget (SEG 1075-1087). - Michelin Boulevard water-line (Davis Plumbing & Sewage LLC) — Award approved; low bid $157,547.25 + 10% contingency = ~$173,301.98; funded from utility water capacity funds (SEG 1218-1239).
All items were approved by unanimous voice vote as recorded in the meeting transcript.

