Hamilton Township approves GMP 2 with Conger Construction for new Public Works building

Hamilton Township Board of Trustees · September 17, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Trustees approved Guaranteed Maximum Price (GMP) #2 with Conger Construction and heard an update on the Public Works replacement facility; project budgeted at $7.5 million with a reported $169,000 overage that is covered by built-in contingencies.

Trustees on the Hamilton Township Board approved Guaranteed Maximum Price (GMP) #2 with Conger Construction Group for the township’s Public Works replacement facility and heard a multi‑month project update from staff and the construction team.

The board heard from Mister Wright, the township administrator, who introduced Nick Romer of Conger Construction and Randy Merrill, the project’s lead architect. Nick Romer said the construction manager‑at‑risk (CMR) model has involved contractors earlier in the design process and allowed the team to lock some material pricing. “The township's budget was $7,500,000.0, and I'm happy to report we've hit it. We have, however, gone over by a $169,000,” a Conger representative said, noting about $700,000 in contingencies and a $300,000 owner contingency that could be returned to the township if unused.

The administrator and Conger described steps already taken: six firms submitted proposals, Conger was selected and named CMR in January, the team established a first GMP in June to secure favorable steel pricing, and prefabricated steel has been ordered. Mister Wright said the township has intentionally saved funds over several years — roughly $2–2.5 million — to make a one‑third down payment and limit long‑term debt, which reduces total interest costs over the life of the borrowing.

Trustees asked about subcontractor selection; the CMR and design team said they vet subs and that township staff may exercise veto authority for firms with problematic past performance. On schedule, staff said the project anticipates completion in 2026.

The board moved and approved resolution 25‑0917D to accept GMP #2 with Conger Construction. Trustees recorded affirmative responses during roll call (Mister Cordray and Mister Sousa answered “Yes”).

Next steps described by staff include finalizing subcontracts, continuing value‑management exercises, and beginning site work following the formal GMP approval.