Cowlitz County delays several road capital projects; engineers cite permitting and funding timing
Summary
County engineers told commissioners multiple big road projects were delayed, leaving capital spending well below budget; South Cloverdale, Dyke Road reconstruction and Tower Road were highlighted along with FEMA timing for Pleasant Hill and a failed culvert on Barnes Drive.
Susan Eugenis, Cowlitz County engineer, told commissioners the county did not complete the 2025 capital program, which explains a large disparity between budgeted and spent capital funds.
Eugenis said South Cloverdale is a roughly $7 million project with about $6 million expected from external sources; the county has spent approximately $150,000 to date and expects the project to progress next year. She said Allender Road bridge replacement is grant funded and was awarded, and Tower…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat