Louisa County school construction updates: middle school near completion; CTE building progressing

Louisa County School Board · December 3, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Board presenters reported the new middle school is about 93% complete with $21,990,355.50 spent (84.59% of budget) and the CTE building is progressing with CMU work; a no-cost chiller upgrade for the CTE project was noted and project finance figures were provided.

Board presenters gave progress reports on two capital projects: the new middle school and the career and technical education (CTE) building.

A facilities presenter described recent exterior and site work at the middle school, including road resurfacing and a new bus drop-off lane to serve special-education classrooms on the addition's lower level. The presenter said the auxiliary gym had been essentially doubled and praised the finished spaces.

A project finance representative said there were no change orders for the middle school and reported $21,990,355.50 spent to date, representing 84.59% of the budget, and that the project is 93.43% complete. "So we are, under budget, and we are set to open up after the first," the finance representative said.

On the CTE facility, the facilities presenter said CMU/block work has advanced substantially and one slab remains to be poured because of pending electrical and fire-pump connections. The presenter said work would reach the roof in March. The finance report for the CTE project listed expenditures of $7,462,921.51, representing 18.99% of its budget, with 25.77% of the project complete. The board recorded a no-cost change order to upgrade the CTE chiller.

Board members responded positively and asked no follow-up technical questions during the meeting; presenters noted a small punch list remains on installations and that final steps would proceed over the next weeks.