Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Contractor reports Kings High School project $3.5 million under budget; turnover targeted for Dec. 2027
Summary
HTC, the general contractor for the new Kings High School, told the board the project is on schedule with structural steel planned for January and a December 2027 turnover; the contractor said the current contracts total about $104 million and the project is approximately $3.5 million under budget.
HTC general contractor representatives updated the Kings Local Board of Education on the new high school construction project and introduced the final GMP (guaranteed maximum price) package the board will consider.
Bill Braback of HTC told the board the project reached a major milestone when crews poured the concrete core that will top out the building. "We started masonry at the arena side of the building...the first masonry foundation walls have started as of today," Braback said. He said exterior foundation work on the academic wing is roughly 50% complete and structural steel is scheduled to begin in…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat

