Committee reviews three renovation options for CVPA/CSMB; cost and phasing questions remain

Real Estate Committee, St. Louis City · December 16, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Design team presented three options for the CVPA and CSMB renovations — full-scope Option A, reduced Option B, and north-only Option C — highlighting secure vestibules, circulation and an ADA elevator; board members pressed for final costs, parking counts and phasing details.

Courtigan Clark’s design team presented three distinct renovation packages for the CVPA and CSMB buildings and asked the St. Louis City Real Estate Committee for direction on scope and phasing.

"Option A is the project as it was recently bid or rebid back in August '26," a presenter said, describing a package that would add both north and south secure entry vestibules, a south-entry elevator, renovated south parking, courtyard improvements and a renovated dance suite. Erin Mueller, associate vice president with Courtigan Clark, told the committee the full-scope plan would relocate the CVPA administration suite from the second floor to the first level so it sits adjacent to the new secure entry.

The design team emphasized safety…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans