Dorchester County updates dozens of projects; wastewater expansion 56.7% complete, $113.9M expended
Summary
County staff told the council that the MUSC St. George health facility is nearing substantial completion, the Dorchester Regional Water Interconnect Phase 1 has ~95% of mainline pipe installed, and the Lower Dorchester wastewater expansion is 56.7% complete with $113,900,000 expended to date.
County staff provided a multi-department capital-projects update at the Nov. 17 Dorchester County Council meeting covering land development, transportation, water and wastewater projects.
Adam Davis provided project-level status reports: conceptual designs for the Furman mixed-use project will be available for the next county council meeting; the coroner's office is undergoing waterproofing and mechanical/electrical/plumbing rough-ins; Oak Brook Sports Complex held a pre-construction kickoff on Oct. 23 and will begin parking-lot demolition and conduit work; and…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat