Moccasin Bend wastewater modifications discussed; no board action planned

Industrial Development Board of Chattanooga · December 2, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Board members reviewed a quarterly wastewater project update for Moccasin Bend tied to the consent decree; phase 1 is scheduled for August 3, 2026 and substantial completion July 3, 2029. The wastewater representative was absent and no board action was requested.

Chair (Speaker 1) introduced a quarterly project update by the wastewater department and Jacobs Engineering for Moccasin Bend modifications, part of the consent decree program. Staff noted phase 1 dates (08/03/2026 start and 07/03/2029 substantial completion) and that the project includes new construction to process material into pellets using high-intensity heat as part of a pilot.

The board’s wastewater representative was absent; staff said no board action was planned at this time and agreed to place the item on the next agenda when the wastewater contact (Mark Heinzer) could attend. No public comments or votes were recorded on this item during the meeting.