Pasco aquatic center 55% complete; team targets Memorial Day 2026 opening

Pasco Public Facilities District Board · December 17, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Owner's representative reported the aquatic center is about 55% complete, owner’s contingency is just under 3%, glazing and permanent power work are imminent and the team anticipates opening on Memorial Day weekend 2026. Staff outlined upcoming operational steps including lifeguard recruitment, naming and rate setting.

The Pasco Public Facilities District heard construction and operations updates Tuesday indicating substantial progress toward a planned Memorial Day weekend 2026 opening for the aquatic center.

Owner's representative Jake reported the project is roughly 55% complete. "We're running [owner's] contingency at just under 3%," he said, and described recent work including formed indoor pool walls, imminent glazing installation and permanent power being…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans