Selectmen approve Change Order 15 for fire headquarters; project timeline pushed to early February

North Brookfield Board of Selectmen ยท December 3, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Change Order 15, covering several unforeseen items on the fire headquarters project including added insulation, meter disconnect and ceiling fans, was approved; the contractor and town staff now project a completion around Feb. 1 instead of mid-January.

The North Brookfield Board of Selectmen approved Change Order 15 on Dec. 2 to address additional work at the new fire headquarters.

Town staff described multiple PCOs (project change orders) included in Change Order 15. Notable items listed by staff were: added insulation where existing sheetrock was removed ($10,466.73); a tank-piping credit ($3,278.45) for relocated piping; exterior masonry patching ($861.43); second-floor wood trim ($3,640.65); a meter disconnect to allow safe external shutoff ($5,848.08); a telecom conduit credit ($870.08); and two ceiling fans with wiring for the large second-floor meeting room ($2,929.91). Speaker 2 said the insulation and ventilation work requires careful sequencing and that the contractor now anticipates completion closer to Feb. 1.

After discussion Speaker 1 moved to approve Change Order 15; Speaker 3 (John Carroll) spoke and the board approved the motion by voice vote. Staff said these measures will improve the building's weatherproofing and habitability.