Atoka municipal authority approves $148,001.86 pay application for headworks project and pays $29,230 to Wallen Engineering
Summary
The municipal authority approved pay application No. 12 to HCCCO for $148,001.86 for the headworks project and approved a $29,230 invoice to Wallen Engineering for engineering oversight.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Atoka’s municipal authority voted to approve payment applications related to the wastewater headworks project during the Dec. 1 meeting.
The authority approved pay application No. 12 to HCCCO for $148,001.86, which staff said covers recent construction work on the headworks. Wallen Engineering, the project manager/oversight firm, reported parts are still arriving and estimated the overall completion window as mid- to late January; a Wallen representative (Randy) provided timeline commentary.
The authority also approved invoice No. 10 from Wallen Engineering for $29,230 to cover engineering and oversight fees. A trustee asked about the remaining balance for engineering services and staff acknowledged an outstanding amount (about $74,000 was discussed in the meeting). Both pay applications and the invoice passed by roll-call votes.
Wallen Engineering will continue construction oversight and the city expects to bid additional water and wastewater projects in coming months, according to staff remarks at the meeting.