Harrison Street streetscape ahead of schedule but bollard installs delayed by engineering sign-off

Hollywood Community Redevelopment Agency · December 11, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Burkhart Construction reported progress on Harrison Street phases; Phase 1 opened Nov. 20 and Phase 2 began Nov. 21. Crash‑rated bollards in contractor possession await Florida engineer sign-and-seal for building-department approval, prompting board direction to expedite approvals and coordinate installations to limit merchant disruption.

The Hollywood Community Redevelopment Agency heard an update Dec. 10 on the Harrison Street streetscape, where contractor Burkhart Construction reported the project is generally ahead of schedule but still requires final work that will briefly disrupt sidewalks and parking.

Burkhart project manager Nick Fasulo said the six-phase project opened Phase 1 on Nov. 20 after starting Sept. 29 and began Phase 2 on Nov. 21. Work includes demolition and removal of existing pavers and concrete bands, new irrigation, regrading, tree pit header bands, new bollards and…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans