Sunset Park school construction about 45–50% complete, contractor says; GMP and billing details presented
Summary
District staff and the Lightyear/Leitner construction team told the Rock Hill School Board that the new Sunset Park project is roughly 45–50% complete, utilities are largely tied in and the guaranteed maximum price and monthly progress billing were discussed.
District operations staff and the construction team provided a status update on the Sunset Park school project, showing drone and interior footage and listing completed site and building milestones.
Darren Wilson, assistant superintendent of operations, introduced a Lightyear/Leitner team that included site superintendent Dexter Pinkston, project manager…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat