Urbana Park District updates board on pavilion construction, Perkins Road work and Prairie/Weaver phase 2 planning
Summary
District staff told the board Dec. 9 that the pavilion structure is erected but masonry work is delayed by weather; three change orders reduced contingency to roughly $18,031 and the contract balance stands at about $973,054 with $275,000 in pay applications. Perkins Road and Prairie/Weaver phase 2 engineering and funding work will return to the board in January.
District staff provided a series of capital-project updates at the Dec. 9 board meeting, covering the pavilion, Perkins Road site work, and phase 2 design work for Prairie/Weaver.
Derek presented mid-November photos showing the pavilion structure erected but noted masonry and finishing work are delayed by cold weather. He described three change orders: (1) a pre-construction change to meet DBE goals that altered the source of the pavilion structure; (2) a $13,500 change covering an added light pole and a swap to a district-standard water fountain; and (3) a…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat