Citizen Portal
Sign In

Lifetime Citizen Portal Access — AI Briefings, Alerts & Unlimited Follows

Board approves $182,829 change order and 58‑day extension for Denham Springs High field house

Livingston Parish School Board · December 19, 2025

Loading...

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Coleman Partners recommended approval of Change Order #3 from Blunt Construction adding $182,829 and a 58‑day extension to the Denham Springs High School field‑house project, bringing the total to $6,413,214 with a February 24, 2026 completion date.

The Livingston Parish School Board approved Change Order #3 for the Denham Springs High School field house, adding $182,829 in contract costs and extending the project schedule by 58 days.

Jeff LaRosa of Coleman Partners Architects presented the change order on behalf of Blunt Construction, reporting a new total project sum of $6,413,214 and a revised completion date of Feb. 24, 2026. "The new total sum for this project will be $6,413,214 with a completion date of 02/24/2026," LaRosa said, and he told the board that Coleman Partners and project consultants had reviewed the contractor’s documentation and recommended approval.

Board discussion noted that the change order bundles a number of items and represents the final change order before project completion. Mister Cecil Harris moved to approve Change Order #3; the motion was seconded and approved by voice vote.

The board did not read a line‑item breakdown into the record at the meeting; LaRosa and staff said consultants had reviewed the contractor’s submission and recommended approval.