County Grants Time Extension for Juniato Terrace Water Main Project to Jan. 16, 2026

December 19, 2025 | Mifflin County SD, School Districts, Pennsylvania


This article was created by AI summarizing key points discussed. AI makes mistakes, so for full details and context, please refer to the video of the full meeting. Please report any errors so we can fix them. Report an error »

County Grants Time Extension for Juniato Terrace Water Main Project to Jan. 16, 2026
County staff told the board that the main construction for the Juniato Terrace Water Main Extension was delayed primarily by North Shore Railroad's requirement that an inspector be on-site during the horizontal boring under Roundhouse Road and several railroad tracks.

The engineer and contractor Geiger Brothers agreed that the schedule required a time extension but did not require an increase in the contract price. Staff recommended, and the board approved, a new substantial completion date of Jan. 16, 2026.

Officials said the additional time will allow the contractor to finish the directional boring and related pipe work without remobilizing. The board approved the extension during the meeting with no roll-call vote recorded.

Next steps: county engineering staff will continue oversight and coordinate with North Shore Railroad and the contractor to meet the revised completion date.

Don't Miss a Word: See the Full Meeting!

Go beyond summaries. Unlock every video, transcript, and key insight with a Founder Membership.

Get instant access to full meeting videos
Search and clip any phrase from complete transcripts
Receive AI-powered summaries & custom alerts
Enjoy lifetime, unrestricted access to government data
Access Full Meeting

30-day money-back guarantee