Montgomery County board hears updates on Percy Julian, Capitol Heights and multiple school renovations
Summary
Board members received construction and facilities updates: Percy Julian High is 15% complete with a Dec. 2027 turnover target, Capitol Heights pre-bid work is underway, South Lawn change order No.2 would add about $153,000, and districtwide media center and athletic projects are progressing.
Montgomery County Board of Education members received a broad facilities update Dec. 11 that covered progress on major construction projects, pending change orders and a slate of building renovations across the district.
Laura Penn of Volker reported the new Percy Julian High School project is about 15% complete and remains on track for turnover in December 2027. She told the board the contractor has started overhead structural steel and that concrete work and storm shelter footings are under way. The board was shown a MultiVista fly-through of the site.
Capitol Heights Middle School has…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat