Planning Commission recommends limited CO relief for Benders Cove after utility relocation delay

Mount Juliet Municipal and Regional Planning Commission · December 19, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Developers sought to change the certificate-of-occupancy trigger for Benders Cove from 25 to 75 while a Piedmont gas-main relocation proceeds; the commission instead recommended a smaller increase (25 additional COs, for 50 total) and forwarded that recommendation to the Board of Commissioners.

Meritage Homes’ development team asked the Mount Juliet Planning Commission on Dec. 18 for temporary relief from a PUD condition that ties off-site Benders Ferry Road widening to certificates of occupancy.

Kelly Frank, the civil engineer representing Meritage Homes, said crews encountered an unmarked portion of a Piedmont gas main that must be relocated and that Piedmont proposed a roughly 45-day…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans