Council OKs $93,342.69 change order to add ADA features and batting‑cage electrical work at Frasier Field
Summary
Council approved a $93,342.69 change order to add ADA-compliant dugout benches, companion wheelchair pads and electrical work for batting cages at Frasier Field; the project remains within budget and the motion passed 5–0.
Get email alerts on the Parks topic
No spam. Unsubscribe anytime.
The City Council approved a change order totaling $93,342.69 for Frasier Field improvements to add ADA‑compliant features and electrical work for batting cages.
Community Services Director Adriana Nava said that after plan review, the project required benches with backs and companion seating (additional concrete pads) to meet ADA standards for eight dugouts; electrical work for lighting and batting‑cage outlets was also added. Nava said the original contract was about $375,000, the change order adds about $93,000, and the total project cost would be $468,851.69 — leaving a remaining budget of roughly $98,724.31 from the allocation of $567,576 (a mix of Measure P and CDBG funding).
Council asked about maintenance and protection of the batting cages and electrical outlets; staff said outlets would have protective covers and the facilities would be locked when not in use. The council moved to approve the change order and the motion passed 5–0.
The change order brings the dugouts and related facilities into compliance with ADA bench and circulation requirements and funds electrical infrastructure for planned batting‑cage equipment.