Rockport‑Fulton ISD: High‑school project 88% billed; elevator inspection delays substantial completion to March 2026
Summary
District staff told the board the new Rockport‑Fulton High School is 88% billed with $34,670,000 authorized; a failed elevator inspection and punch‑list work pushed the district to target substantial completion in March 2026 and schedule final TCO inspections before reopening classrooms.
The Rockport‑Fulton ISD high‑school construction project is largely built but not yet ready for students after recent inspection setbacks, district presenters told the board.
"The progress for the billing is 88% complete," said Presenter (S16), reporting that $34,670,000 has been authorized on the project and that substantial completion is scheduled for March 2026. Classroom flooring, furniture installation and locker‑room finishes are complete in many areas, and…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat