Director reports pump and electrical delays; sled hill not yet open
Summary
City director told the council a contractor delay in delivery of a pump and electrical equipment has delayed completion of a sled-hill infrastructure project; staff expect the project to be finished within about a week, pending equipment arrival, and moved the report to file.
Get email alerts on the Parks Operations topic
No spam. Unsubscribe anytime.
At the informational director's report, the Director (name not stated) updated the council on a parks infrastructure project tied to the sledding hill. He said the project is roughly 80'90% complete but completion is delayed because a key pump and electrical equipment are on backorder; staff have a meeting scheduled with the contractor to review delivery timelines. "I think last I heard, the project should be completed sometime next week," the Director said.
The director explained that the city cannot revert to the temporary water service used in a prior year without incurring additional expense because the permanent water service is now installed in the same location. He described the underground work as largely finished and said that once equipment arrives staff will install it in the shed at the top of the hill and, if natural snow levels remain insufficient, the city could make snow immediately to open the hill for use.
A councilmember moved to receive and place the director's report on file; the motion was seconded and approved by voice vote. No specific reopening date was set during the meeting; staff will follow up with the contractor and report timing to the council.