Council briefed on Fire Station 1 change orders, liquidated damages and revised completion timing

Hoover City Council · November 21, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City staff asked the council to accept change orders 1–20 for Fire Station 1, identifying an $11,416.83 uncovered cost and noting the project is in liquidated damages; turnover is now likely in early January rather than early December.

Mister Miller (Speaker 8) explained the council needs to accept change orders 1 through 20 for Fire Station 1 and said all were built into the contingency allowance except for $11,416.83: “So that is the amount that this would take and elevate the cost of that project by.”

Speaker 8 added the city is assessing liquidated damages for late completion, noting the contractually required completion date was Sept. 1 and the city is collecting about $500 per day. When asked about turnover, Speaker 8 said contractors had suggested early December but the speaker would count on turnover around the first of the year.

Council did not vote at the work session; staff said a budget amendment will follow after the council approves the change orders.