Council advances Ralston Avenue roundabout financing and property appropriation to move storm-sewer work forward
Summary
The Defiance City Council adopted a third-reading tax-exemption/TIF ordinance to help close funding gaps for the Ralston Avenue roundabout and considered an ordinance to appropriate an interest in 1203 Ralston Ave to install storm sewer; councilmember O'Donnell said the appropriation is needed to file in court to resolve title issues.
Get email alerts on the Ralston Roundabout topic
No spam. Unsubscribe anytime.
The Defiance City Council on Dec. 2 adopted a third-reading ordinance establishing a tax-exemption and tax-increment financing arrangement to cover remaining costs for the Ralston Avenue roundabout project and moved forward on a related property appropriation needed for storm-sewer construction.
Councilmember O'Donnell explained the financing vehicle as targeted to cover project costs not paid by grants or low-interest loans, saying it would capture 75% of the increased assessed value for 10 years for the Legacy Living senior development parcels. "This is the third and final reading," O'Donnell said, describing the proposed TIF as a way to apply increased property value to outstanding project expenses.
On the related property action, O'Donnell told council the city has title concerns for a parcel at 1203 Ralston Avenue and that passage of an appropriation ordinance is required "in order to take the next step, which is file a complaint in the court of common pleas," enabling the city to resolve ownership and move the storm-sewer work forward.
Council moved to adopt the TIF ordinance and recorded affirmative roll-call votes from the councilmembers present. The appropriation ordinance was presented as a third reading with council discussion focused on the legal step needed to permit the city to proceed with right-of-way and storm-sewer construction; council did not record further debate on conditions in the transcript excerpt.
The council's actions are procedural steps toward completing the Ralston Avenue roundabout: adopting the financing plan to fill funding gaps and authorizing an appropriation to address title issues on the parcel needed for storm-sewer installation. The city will use its next procedural steps to finalize acquisition and construction scheduling.