CTE building 70% complete; locker rooms nearly finished and bond contingency remains under $5 million
Summary
Construction managers told the board the new CTE building is roughly 70% complete with permanent power and elevator delivery scheduled soon; locker room renovations are substantially complete and the 2019 bond contingency balance remains just under $5 million.
Construction managers from CS Arch and Jacobs updated the Newburgh City School District board on several capital projects, saying the new Career and Technical Education (CTE) building is roughly 70% complete and locker room renovations are nearly finished.
Tom Ritzenthaler, speaking for CS Arch, said interior fit‑out work is ongoing and permanent power for the CTE building is scheduled; "we're about 70%…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat