Carlisle board reviews Ken Millen Stadium renovation plan, estimates $1.72–$1.76 million for next phase

Carlisle Area School District Board · December 5, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

District administrators presented a phased athletic-facility plan and a proposed renovation of east-side bleachers and under-bleacher space at Ken Millen Stadium, with the current construction estimate between $1.72 million and $1.76 million and a 16–20 week schedule to be ready for fall 2026 sports.

District athletic-facility planning returned to the Facilities Committee Dec. 4 with details for the next phase at Ken Millen Stadium: under-bleacher renovations and east-side bleacher upgrades to create team rooms, a visiting-team locker room, a training room, upgraded restrooms (including family restrooms), and storage.

Dr. Michael Black said the district’s 2019 feasibility work envisioned a three-phase program costing roughly $10–$12 million to complete all projects. With about $3 million available in 2025, the district completed the turf field, a stadium of roughly 750 seats, and tennis courts, and is now proposing the east-side renovation as the next priority. Dr. Black told the committee the current contract bid places the stadium renovation between $1.72 million and $1.76 million; the construction schedule is estimated at 16–20 weeks, with a target to be completed and ready for fall sports in 2026.

The renovation will provide heated, non-winterized team rooms and expanded support spaces so teams will not need to use school hallways or porta-potties during inclement weather. The plan includes three team rooms on the west side and five on the east side, plus a visitor locker room and training room. The district also expects to use a portion of remaining project funds to buy lockers, benches, training-room equipment and other furnishings.

Board members asked about ancillary issues — a small technology/trailer building near the tennis courts, conditions for existing home-side bathrooms, lighting and preserving home-field advantages — and were told the administration is evaluating options including demolition or renovation of the small building and that certain home-side bathrooms are not part of the current scope. Dr. Black said the full athletics program — tennis, turf, and these renovations — represents an investment in the range of $5 million over multiple years while prioritizing projects to fit available funds.

No final contract award was taken at the meeting; the committee will return proposed contract documents and appropriation details for board approval in the coming weeks.