Rosemount council orders 2026 Street Improvement Project; assessments estimated under $600,000

City of Rosemount City Council · December 3, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The City of Rosemount adopted a resolution to order the 2026 Street Improvement Project (City Project 2026-01), authorizing final plan preparation and bid advertisement. Project cost is about $2 million; preliminary special assessments total just under $600,000 with estimated per-parcel assessments of $3,000–$4,000 and a 10-year term.

The City of Rosemount on Dec. 2 adopted a resolution ordering the 2026 Street Improvement Project (City Project 2026-01), authorizing staff to finalize plans and advertise for bids.

The council's action followed a presentation by the city engineer, who described the project area as the southern portion of the city north of County Highway 46 between Shannon Parkway and Chippendale, plus a few streets west of Chippendale. The work is largely pavement reclamation, spot curb-and-gutter repairs, ADA sidewalk and pedestrian-ramp improvements and limited utility work; two alternate items — repaving the lift station at Shannon and 160th (Highway 46) and repaving the trail through JC Park — were described as separate and not part of the assessments.

The engineer said the overall project cost is about $2,000,000 and that special assessments are currently estimated at just under $600,000 total. Preliminary per-parcel assessments were shown in materials at roughly $3,000–$4,000. Assessment calculations will be finalized after the contract bid is known; the stated approach was to take 35% of the street improvement cost and divide that equally by the number of properties along the corridor. Assessment payments can be placed on property taxes over a 10-year term. An assessment hearing is planned for March 17 — after bid opening — to set final assessment amounts.

Council received no public testimony during the improvement hearing. Council member Klimpel moved to adopt the resolution ordering the project; the motion received a second and passed on a 4–0 roll call.

What happens next: staff will finalize plans and specifications and advertise for bids; the project schedule presented anticipates a bid opening and an assessment hearing in March. Property owners in the project corridor should expect a final assessment notice after bids are awarded and the required statutory assessment steps are completed.