Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Water Infrastructure topic
No spam. Unsubscribe anytime.
Council approves HDR amendment for pump station design; staff cites large construction estimate and seeks FEMA/NEMA funding
Summary
The council approved a $26,085.34 amendment to HDR Inc.'s design contract for the Seward Lehi interior pump station, and staff said 90% plans have been submitted to FEMA and NEMA; staff also described a construction estimate and said additional grant funding will be sought before bidding.
Get email alerts on the Water Infrastructure topic
No spam. Unsubscribe anytime.
The Seward City Council voted Dec. 23 to approve Amendment No. 1 to the agreement with HDR Inc. for design engineering services on the Seward Lehi interior pump station in the amount of $26,085.34.
Mike (speaker 6) told council HDR submitted 90% plans and specifications to FEMA and NEMA; the amendment covers additional design work to reach that 90% milestone and prepare the project for future bidding. Mike stated staff will defer final design completion and bidding until additional construction funding is secured.
During his remarks, Mike said a construction cost was currently estimated at $4,500,000,000. The transcript records that figure; staff said they anticipate seeking up to roughly 75% cost coverage from FEMA/NEMA similar to prior phases. The council approved the amendment to complete phase 1 design and directed staff to pursue grant funding and return with bid-ready materials when funding is in place.
Because the construction cost figure stated in the meeting is unusually large for a municipal pump station, reporters and staff should verify that number with engineering and the finance office before publication; the figure is recorded here as stated in the meeting.

