Board approves reroof and stadium repairs, hears campus construction progress and timelines

Liberty Hill Board of Trustees · December 4, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Trustees approved bond‑funded contracts for an administration annex reroof ($312,690.75 total) and stadium erosion repairs (~$165,330). Staff reported multiple campus projects nearing completion, with fire finals and services gating teacher move‑in dates.

The Liberty Hill ISD board on July 15 approved two bond‑funded construction items and received a wide‑ranging construction update showing most summer projects on track for fall openings.

Contract approvals: trustees approved a Balfour Beatty reroof of the administration annex/18+ facility in the amount of $262,690.75 with a $50,000 contingency (total $312,690.75) funded from the 2021–2023 bond program; the board also approved Price and Sons Construction to perform concrete flatwork and rock riprap at the Liberty Hill High School Panther Stadium (contract $135,330 plus $30,000 contingency, total ~$165,330), also funded from the bond program. Trustee Ferguson moved the reroof motion and Trustee Neighbor seconded; Trustee Major made the motion on the stadium work and Trustee Ferguson seconded; both motions passed by voice vote.

Project status and timelines: Dustin Aiken reviewed relocations of portables (Megatron portable moved to the high school for the Success Academy/DAEP), progress on Tierra Rosa Elementary (gym bleachers and flooring complete, final fire inspection scheduled), Legacy Ranch High School finish work, technology‑building substantial completion expected Sept. 1, and athletic‑field work (turf complete; track surfacing and field turn‑overs planned in the coming weeks). Aiken also said Ubiquiti (internet service provider) has delayed permitting but has guaranteed service to Tierra Rosa and Legacy Ranch by July 26.

Move‑in and safety gating: several trustees pressed for exact move‑in timing; Aiken said access to new campuses for staff depends on final fire approvals (tentative dates were discussed for late July and early August). The board discussed traffic and striping near campuses — staff said the city had changed striping in an area and requested the district fund restriping (city estimate cited around $30,000) and that district crews may seek a better internal price and city permission to repaint the configuration.

Other actions and appointments passed that night included routine consent items, personnel approvals, an interlocal wastewater agreement for Legacy Ranch High School, and the appointment of Robert Gillis as principal of Rancho Sienna Elementary.