Board tables $2.76M radio-system change order, approves $395K alerting upgrade

Botetourt County Board of Supervisors · December 17, 2025

Loading...

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

After a technical briefing on revised radio topology, frequency constraints and site changes, the board voted to table a $2.76 million change order for further review and approved a $395,000 change order to outfit Fire Station 7 with alerting equipment.

The board heard a lengthy presentation from communications manager Matt Hinkle about the countyradio upgrade project and proposed change orders.

Hinkle summarized work since a 2022 ORCOM study and explained why the county shifted from joining a regional system to a standalone simulcast design because of spectrum and siting constraints in the quiet zone. The revised plan uses a two-cell simulcast topology with seven sites and a mix of VHF (for broader rural reach) and 700/800 MHz (for southern, more urbanized coverage) and calls for multi-band radios and digital vehicle repeaters to approach industry-standard portable coverage (~95% with DVRS).

Staff presented a cost breakdown for change order 3 (infrastructure, engineering, subscriber upgrades and associated ten-year maintenance obligations) with a subtotal of about $2,760,300 and additional annual maintenance obligations; staff said negotiated concessions and supplier incentives (roughly $500,000+) tied to year-end delivery could be lost if the board delayed approval. The board debated options: removing the Fincastle backup-dispatch upgrade would reduce near-term costs by roughly $400,000, but staff said most other items were required to meet coverage and obsolescence concerns.

After discussion, the board voted to table change order 3 to the January meeting to allow additional review and for returning and incoming supervisors to consider the data; staff cautioned that some negotiated savings would expire if delayed.

Separately the board voted to authorize change order 4, a roughly $395,000 package to provide fire-station alerting equipment for Station 7 and related annual maintenance terms; that motion passed by roll call.

What happens next: staff will return in January with additional detail on change order 3; change order 4 will be executed and incorporated into the radio-project accounting.