Board hears CMAR timelines and coordination challenges for Soddy‑Daisy, North River and other Phase 1 projects
Summary
Facilities staff outlined CMAR (construction manager at risk) selection timelines for multiple Phase 1 school renovations, warned construction could overlap with a YMCA partner’s separate CMAR, and estimated preconstruction and ground‑breaking timing that could push some builds toward 2028.
District facilities staff updated the committee on Phase 1 school renovation projects and a planned CMAR selection process that staff said will require careful coordination when partner organizations use different construction managers.
Mister Witt said architects are producing preliminary designs for several Phase 1 sites, including the Soddy‑Daisy center (transcribed in the meeting as "Saudi Daisy") where planned renovations will add parking and expand drive‑through access to reduce traffic on Highway 27. He said staff expect to advertise for a…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat