Bethel Park SD board hears construction update, approves change order tied to underground spring
Summary
Board received a progress report on the new K–4 elementary school — glazing, interior finishes and rooftop units are arriving — and approved a single change order after workers discovered an underground spring along the lower bus loop, requiring drain tile to be installed; the motion passed 8–0.
Get email alerts on the Construction topic
No spam. Unsubscribe anytime.
A staff member updated the Bethel Park SD board on the district's new K'24 elementary school, reporting that much of the building is now enclosed and interior work is progressing toward an anticipated July opening. "We're gonna open in July," the presenter said, and noted that with cold weather much work has moved indoors and about 90% of activities are now inside.
The presentation listed recent progress: storefront glazing installed on the front of the building, most glazing in place, casework and countertops being fitted, lockers installed on the ground floor, ceramic tile and corridor wainscoting progressing, and drywall installation moving toward paint on upper floors. The speaker said most rooftop units have arrived on site and the contractor plans to set them when weather conditions allow.
The board also considered one facilities change order affecting the Lower Bus Loop. According to the construction update, crews found an underground spring while preparing to pave a portion of the loop, so "we installed some drain tile to control the water and channel it to the proper location on the other side of the road and into the wetlands area," the staff member said, adding that the work uses a unit cost already included in the contract.
Facilities committee chair moved the change order (listed as GC-44, Lower Bus Loop under drain); Mr. Modrak moved the motion and Mr. Scauzo seconded it. Voting was recorded as 8'0yes, 0'no. The staff member said the team will continue to monitor weather for rooftop lifts and hopes to meet the scheduled occupancy timeline.
The board closed the construction discussion with holiday well-wishes and thanks to the project team. The meeting record did not specify an additional dollar amount for the change order; contract unit pricing was described as the basis for the work.