County approves $24,005.09 change order to fix code issues in Public Safety Building basement
Summary
The committee approved Change Order #4 for Ringling Johnson adding $24,005.09 for supply and return ductwork after staff found code deficiencies during ceiling removal; CCS recommended the work and the board approved by roll call.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
The finance committee approved Change Order #4 for Ringling Johnson on the Public Safety Building (PSV) basement remodel in the amount of $24,005.09.
Mr. Bradley moved to approve the change order and Mr. Wolfsey seconded. Randy Darnell of CCS told the committee that after removing the existing ceiling crews discovered multiple items that did not meet code, and the proposed ductwork upgrades correct those code issues. CCS's cost-control team reviewed the proposal and found it fair and consistent with industry standards. County staff supported proceeding.
The committee conducted a roll call; members present recorded their votes in support of the motion and the change order passed. Staff will implement the ductwork work as part of the PSV basement remodel.