Market Street streetscape progress, Main Street closures and traffic-signal timeline announced

Clinton City Council · December 20, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City staff reported the TDOT TAP Market Street streetscape is about 60% complete (331 of 546 project days), Main Street will have block-by-block shutdowns for lateral hookups starting in January, planting of 200+ trees is planned for Feb–Mar, and the Mariner Point traffic signal is delayed pending cabinet delivery (estimated two months).

City administrator Roger Houck told the council the TDOT TAP Market Street streetscape project is roughly 331 days into a 546-day schedule — about 60% complete — and that most of the disruptive work has finished. He said crews will begin about 38 lateral hookups on Main Street in January, requiring block-by-block shutdowns for roughly a month to connect businesses to…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans