Council approves Ferguson Road sewer change order; digester tank damage repair timeline pending

Hampton Township Council · December 19, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Hampton Township approved change order #2 for the Ferguson Road sewer replacement for $11,397.54 and discussed contractor-caused damage to a digester tank that requires manufacturer-fabricated panels and an uncertain repair schedule; construction progress on a larger $60 million project was also reviewed.

Council approved a change order to the Ferguson Road sewer replacement program and reviewed related infrastructure issues Wednesday.

The director of environmental services recommended approval of change order number 2 in the amount of $11,397.54 for additional work required to remove and restore the roadway to PennDOT standards along Ferguson Road; the council approved the change order on a roll-call vote. The director confirmed the change order has been paid.

Council also discussed damage to a digester tank caused when a third-party contractor delivering stone backed into it. The director said the contractor is responsible for repairs and that the manufacturer must fabricate large glass-infused steel panels in Illinois; a repair schedule is not yet available. Officials said draining the tank and handling roughly a half-million gallons of sewage during repairs will be a challenge for staff.

In a separate construction progress report on a large site project, the township’s representative said the project — described in the meeting as about a $60 million undertaking — has progressed well but still has 12 priority punch-list items. The representative estimated substantial completion sometime late in 2026 with final closeout expected in 2028 and noted recent cost increases tied to change-order drawdowns.

Why it matters: The sewer change order and the digester tank damage affect near-term operations, contractor responsibilities and repair logistics for the township’s wastewater system; the larger construction project's punch list and payment drawdowns bear on project timing and final costs.