Commission approves corrected award for water treatment plant admin building hardening
Summary
Commission approved a corrected award amount for the water treatment plant administration building hardening project after staff identified a $400 Scribner's error; the amended contract amount of $349,810 was accepted unanimously.
Get email alerts on the Utilities topic
No spam. Unsubscribe anytime.
Clayton Watkins, Utilities & Engineering, informed the commission Dec. 18 that a math error in the previously posted award for the water treatment plant administration building hardening project had been identified, increasing the award from $349,410 to $349,810. The corrected amount was presented with revised agenda memos and the commission approved the award unanimously with no further questions.
Staff indicated the correction was clerical and there was no further change in scope or contractor selection.